Level Crossing Removal Project

Rail | Multiple Locations, VIC

Level Crossing Removal Project

Overview

The dangerous and congested crossing between Skye and Overton Roads in Frankston required a removal solution that improved safety and reduced congestion. Dura-Base mats provided essential temporary access in this constricted, high-traffic environment.

Dangerous and Congested Crossing Removal

Dangerous and congested are two words to describe the crossing between Skye and Overton Roads within the suburb Frankston. It’s a high traffic railway crossing with limited workspace for construction. The purpose of their endeavour is to improve safety, limit congestion while also maintaining the environment by constructing a rail over the road.

Problem

The challenge was to do works on the railway while maintaining a strict schedule for the train timetable and allowing the constant flow of traffic in a compact space.

Key challenges that Level Crossing Victoria faced were:

  1. Working in a congested, high traffic area

  2. Working in a narrow constricted space for construction

  3. Remediation

Temporary Access Track for Heavy Machinery

The solution to the problem was to create a temporary access track to the site using Dura-Base mats. Allowing access for the drills, piling pads and cement mixers to create a foundation for the over the railroad. Stabilising the ground while also creating a seamless path for the heavy machinery. By doing so, the piling pads were able to be used over multiple sites, reducing the number of trailers needed on site and reducing the amount of needed crush rock from 850mm to 350mm. Thereby, decreasing the time needed to shut down the road for the residing members of Frankston.

Results

Residents on Frankston could breathe easier as the boom gates were removed and the traffic is flowing freely. Currently, the Level Crossing Removal Authority is working tirelessly to remove all boom gates within Victoria. Removing the dangerous crossing has impacted the 10,000 people who drive through every day at Frankston. JWA’s part in the project was a success as the matting was used as a remedy for the constricted area while also not affecting the nearby environmentally sensitive wetlands.

Project Details

Project Name Level Crossing Removal Project
Industry
Location Multiple Locations, VIC

Key Benefits

Resource Conservation

  • Reduced needed crushed rock from 850mm to 350mm
  • Piling pads used over multiple sites
  • Reduced number of trailers needed on site

Emission Reduction

  • Decreased time needed to shut down the road
  • Less material transport due to reduced rock requirement

Minimised Time On Site

  • Seamless path for heavy machinery improved efficiency
  • Rapid installation in constricted areas

Soil Conservation

  • Not affecting nearby environmentally sensitive wetlands
  • Stabilised ground for heavy machinery
  • Successful remediation of the area

Start Your Project

See how our solutions can work for your next project.

Get a Quote

Gallery

Multi-purpose JWA mats
Piling platform at rail level crossing works
Road protection composite mats
Temporary Piling Platform in Rail Corridor

Multi-purpose JWA mats

Trusted by Industry Leaders

Proven Performance

JWA's composite matting solutions have been trusted by industry leaders across Australia for over a decade.