WestConnex New M5
Building | Sydney, NSW
Overview
The New M5 twin underground motorway tunnels required a stable working platform for structural works. Dura-Base mats were instrumental in suppressing dangerous silica dust and providing access for heavy machinery in the confined tunnel environment.
The New M5 is Under Construction
The New M5 seeks to provide twin underground motorway tunnels to alleviate congestion and support Sydney’s long term economic and population growth. The project is valued at 4.34 billion and will be 9 km long, located from Kingsgrove to the new St Peters interchange.
Large part of the project took place within a tunnel. Challenges include having stable working platform to install support beams for structural integrity of the tunnel. As the ground was found to have silica dust, the use of imported fill became untenable. The silica dust had the potential to contaminate the gravel and any time a vehicle drove over the ground, toxic substances would have been released into the air. Workers therefore had to monitor air quality and wear protective equipment the entire project.
Dura-Base Supresses Dust and Protects from Crystalline Silica
As an engineering control, Dura-Base mats were used to suppress dust and minimise the risk of exposure to crystalline silica. Safeguarding the workers from life threatening diseases caused by the crystalline silica.
The thick 105mm interlocked mats served as a temporary access and used to stabilise the ground for for an SPMT to install horizontal beams. Uneven ground would have resulted in the machine unable to gain entry in the tunnel due to the unstable ground.
Once the installation was complete, the workers had to excavate another level down to install more beams. The mats were easily removed and reinstalled down afterwards. Preferable to imported fill as it would have increased the amount of truck movements and would require copious amount of time to retrieve.
Results
The mats were reused at both the Western and Eastern End of Tunnel. Once the beams were installed, the mats could be picked up without disturbing the underlying ground containing silica.
Project Details
Key Benefits
Resource Conservation
- Mats reused at both Western and Eastern ends
- Eliminated need for imported fill
- Reduced material transport logistics
Emission Reduction
- Suppressed dust and minimised silica exposure
- Reduced truck movements for fill import/removal
- Safeguarded workers from respiratory diseases
Minimised Time On Site
- Mats easily removed and reinstalled for multi-level excavation
- Access established quickly on uneven ground
- Avoided time-consuming fill retrieval
Soil Conservation
- Prevented disturbance of silica-contaminated ground
- Acted as engineering control for dust suppression
- Protected underlying substrate
Related Products
Gallery



DuraBase Mats as Platform for Tunnel Beam Installation
Proven Performance
JWA's composite matting solutions have been trusted by industry leaders across Australia for over a decade.